File #: ID#20-7825    Version: 1 Name: Approve Utility Work By Highway Contractor
Type: Action Item Status: Passed
File created: 5/28/2020 In control: Public Works
On agenda: 6/18/2020 Final action: 6/18/2020
Title: Approve Utility Work by Highway Contractor Agreement (UWHCA) between the Florida Department of Transportation (FDOT) and the City of Clearwater for the FDOT Utility Relocation at US19 and Harn Blvd Project (20-0007-UT) and authorize the appropriate officials to execute same and adopt Resolution 20-29.
Indexes: **, 2. Economic & Housing Opportunity , 4. Environmental Stewardship
Attachments: 1. UWHCA Agreement.pdf, 2. Utility Work Estimate.pdf, 3. Location Map.pdf, 4. Resolution 20-29

SUBJECT/RECOMMENDATION:

Title

Approve Utility Work by Highway Contractor Agreement (UWHCA) between the Florida Department of Transportation (FDOT) and the City of Clearwater for the FDOT Utility Relocation at US19 and Harn Blvd Project (20-0007-UT) and authorize the appropriate officials to execute same and adopt Resolution 20-29.

 

Body

SUMMARY: 

FDOT is planning to construct a pedestrian overpass at the intersection of US19 and Harn Boulevard. The project includes constructing retaining walls used to support pedestrian ramps on the west and east sides of US19.

 

The City has 8-in. and 4-in. reclaimed water mains on both sides of US19 that conflict with these retaining walls and require relocation.

 

May 21, 2020, FDOT approved the City’s request to enter a UWHCA to relocate the reclaimed mains that conflict with the proposed FDOT construction. This agreement allows FDOT to fund the City’s relocation costs, estimated at $256,300, and include the work in an FDOT procured and managed contract. The proposed relocation work is within a City easement in FDOT ROW.