Approve Engineer of Record (EOR) Supplement Work Order 2 to King Engineering Associates, Inc. in the amount of $110,130 for the East Water Reclamation Facility Influent Pump Station Rehabilitation (13-0016-UT) and authorize the appropriate officials to execute same. (consent)
Body
SUMMARY:
On June 14, 2013, the City Manager approved the initial work order to EOR King Engineering Associates, Inc. to provide a preliminary design for the rehabilitation of the East WRF Influent Pump Station in the amount of $35,632.
On December 24, 2015, the City Manager approved supplemental work order one to provide design of a new influent sewer structure upstream of the Influent Pump Station as required for the temporary by-pass of the Influent Pump Station during its rehabilitation in the amount of $23,203.
Supplemental 2 provides for the completion of the rehabilitation design and bidding services including lining of the existing main from the proposed sewer by-pass structure to the wet well, a corrosion resistant coating for the wet well, an improved Fats/Oils/Grease breakup spray water system, odor control improvements and a new headworks gantry crane for servicing the bar screens for a new work order value of $168,965.
APPROPRIATION CODE AND AMOUNT:
3277327-561300-96664
Funds are available in capital improvement project 96664, WPC Repair and Replacement, to fund this work order.