File #: ID#18-5251    Version: 1 Name: Marshall Street Water Reclamation Facility Digester Demolition
Type: Action Item Status: Passed
File created: 10/9/2018 In control: Public Works
On agenda: 11/1/2018 Final action: 11/1/2018
Title: Award a construction contract to GHD Services, Inc., of Tampa, FL, in the amount of $960,575.83 for the Marshall Street Digester Demolition (09-0024-UT); approve Engineer of Record (EOR) Supplemental one Work Order from King Engineering in the amount of $52,192; and authorize the appropriate officials to execute same. (consent)
Indexes: **, 2. Economic & Housing Opportunity , 4. Environmental Stewardship
Attachments: 1. Bid Tabulation sheet, 2. Recommendation of Award, 3. Section V - Marshall St. WRF Digester Demo.pdf, 4. Supplemental Work Order, 5. Location Map

SUBJECT/RECOMMENDATION:

Title

Award a construction contract to GHD Services, Inc., of Tampa, FL, in the amount of $960,575.83 for the Marshall Street Digester Demolition (09-0024-UT); approve Engineer of Record (EOR) Supplemental one Work Order from King Engineering in the amount of $52,192; and authorize the appropriate officials to execute same. (consent)

Body

SUMMARY: 

This project will involve the demolition, removal, and disposal of the existing digester at the Marshall Street Water Reclamation Facility (WRF). The work includes surveying for asbestos and hazardous waste, preparing an abatement plan, removing and disposing of hazardous and non-hazardous waste, and demolition/disposal of the digester.

 

Two bids were received and GHD Services, Inc., was the lowest responsible bidder in accordance with plans and specifications. EOR King Engineering evaluated the bids and recommends awarding the contract to GHD Services, Inc.

 

November 7, 2013, the City Manager approved an initial work order to EOR King Engineering for design of the demolition of the digester at the Marshall Street WRF in the amount of $84,978.

 

Supplemental 1 Work Order is for increased engineering and inspection services during construction for a new work order value of $137,170.

 

It is anticipated construction will be completed within 200 calendar days from Notice to Proceed.

 

The City of Clearwater’s Public Utilities Department is responsible for owning, operating and maintaining the Marshall Street WRF.

APPROPRIATION CODE AND AMOUNT:

3277327-563800-96664 $960,575.83

3277327-561300-96664 $ 52,192.00

Funds are available in Utility Renewal and Replacement project 96664, WPC Repair & Replacement, to fund this project.