File #: ID#17-3585    Version: 1 Name: Emergency Seawall Repair Change Order 1 Final
Type: Action Item Status: Passed
File created: 5/25/2017 In control: Public Works
On agenda: 6/14/2017 Final action: 6/14/2017
Title: Ratify and confirm Change Order 1 to Waterfront Engineering Inc., of Tampa, Florida, for Emergency Seawall Repairs in the amount of $8,765.58 and authorize the appropriate officials to execute same.
Attachments: 1. Emergency Seawall Repairs RC CO1.pdf, 2. fuller.pdf

SUBJECT/RECOMMENDATION:

Title

Ratify and confirm Change Order 1 to Waterfront Engineering Inc., of Tampa, Florida, for Emergency Seawall Repairs in the amount of $8,765.58 and authorize the appropriate officials to execute same.

 

Body

SUMMARY: 

November 17, 2016, City Council approved emergency seawall repair proposals provided by Waterfront Engineering.

 

During repair to the Fuller Drive seawall along Stevenson Creek, Waterfront Engineering encountered buried debris, from an earlier seawall, which needed to be removed and caused the need for additional fill material and design modifications to the new wall panel depths for an increase of $14,541.68.

 

The seawall repaired on Clearwater Beach North of Opal Sands was completed under the proposed value saving the City $5,776.10 for a net increase to proposals of $8,765.58.

 

APPROPRIATION CODE AND AMOUNT:

0315-93412-563800-539-000-0000 $14,541.68 ST113359

0315-93412.563800-539-000-0000  ( 5,776.10) ST113358

 

Funds are available in capital improvement project 315-93412, City-wide Seawall Replacement, to fund this change order.