File #: ID#14-614    Version: 1 Name: Change Order 1 Smallwood CirDrain/Edgewood Sewer
Type: Action Item Status: Passed
File created: 10/17/2014 In control: Public Works
On agenda: 11/3/2014 Final action: 11/6/2014
Title: Approve Change Order 1 to Rowland, Inc. of Pinellas Park, Florida for the Smallwood Circle Drainage and Edgewood Avenue Sanitary Sewer Improvements projects (11-0057-EN and 10-0027-EN) in the amount of $148,718.00, for a new contract total of $2,493,860.97, approve a time extension of 95 days for completion of additional work and unforeseen field conditions, and authorize the appropriate officials to execute same. (consent)
Indexes: **, 4. Environmental Stewardship
Attachments: 1. Smallwood - Change Order 1.pdf, 2. Smallwood - Edgewood Location Map with Curb 141014.pdf
SUBJECT/RECOMMENDATION:
Title
Approve Change Order 1 to Rowland, Inc. of Pinellas Park, Florida for the Smallwood Circle Drainage and Edgewood Avenue Sanitary Sewer Improvements projects (11-0057-EN and 10-0027-EN) in the amount of $148,718.00, for a new contract total of $2,493,860.97, approve a time extension of 95 days for completion of additional work and unforeseen field conditions, and authorize the appropriate officials to execute same. (consent)
Body
SUMMARY:  
Clearwater City Council awarded a $2,345,142.97 contract on November 7, 2013 to Rowland Incorporated for the Smallwood Circle Drainage Improvements and Edgewood Avenue Sanitary Sewer Improvements projects (11-0057-EN and 10-0027-EN).
 
While working in the neighborhood installing the sanitary and storm pipe, the City encountered substandard base beneath the majority of the existing curb. The lack of base combined with the condition of the curb and the extensive roadway disruption from the storm and sewer work, triggers the need to replace the curb on streets affected by the contract work.
 
Fifty days are requested to complete the additional 5300 linear feet of additional curb work. Another forty-five days are requested to complete other out of scope work due to field conditions including underdrain, pipe removal, sanitary offset, and structure modifications. The contract's new completion date is March 6, 2015.
 
The Streets and Sidewalks Division shall own, operate and maintain the curb improvements once completed.
 
APPROPRIATION CODE AND AMOUNT:
0315-96178-563700-539-000-0000 $83,282.08
0327-96665-563800-535-000-0000 $65,435.92
Funds are available in capital improvement program project 315-96178, Smallwood Circle, in the amount of $83,282.08 and $65,435.92 is available in Utility Renewal and Replacement project 0327-96665, Sanitary Sewer R&R, for total funding in the amount of $148,718 to fund this contract.