File #: ID#18-4244    Version: 1 Name: Approval of Flow Monitoring Equipment Interlocal Agreement with Pinellas County
Type: Action Item Status: Passed
File created: 1/11/2018 In control: Public Utilities
On agenda: 2/1/2018 Final action: 2/1/2018
Title: Approve an Interlocal Agreement between the City of Clearwater and Pinellas County for Flow Monitoring Equipment and authorize the appropriate officials to execute same. (consent)
Attachments: 1. 2. Flow Equip Funding Agreement Pinellas County1-9-18

SUBJECT/RECOMMENDATION:

Title

Approve an Interlocal Agreement between the City of Clearwater and Pinellas County for Flow Monitoring Equipment and authorize the appropriate officials to execute same. (consent)

 

Body

SUMMARY: 

The City has installed sewer system flow monitors in strategic locations to assist the City in identifying portions of the sewer system where infiltration/inflow (I/I) flows are such that additional I/I abatement work is required. These flow meters also serve to demonstrate the effectiveness of completed I/I work.

The City of Clearwater is a member of the Pinellas County Wastewater/Stormwater Task Force (TF). The installation of these flow meters is one of the initiatives identified by the TF that assists in I/I abatement efforts, and the TF has recommended that their members install sewer system flow meters. As such, the County has agreed to provide members of the TF with partial reimbursement for the cost of installing these flow meters. This Interlocal Agreement provides for this funding.

 

APPROPRIATION CODE AND AMOUNT:

0315-96665-337900-000-000-0000 $36,585.00 (Grant Revenue)

To provide partial matching of City funding from the Capital Improvement Projects 315-96665, Sanitary Sewer R&R project.

 

 

USE OF RESERVE FUNDS:  N/A