SUBJECT/RECOMMENDATION:
Title
Approve a purchase order to Murphy Pipeline Contractors of, Tampa, FL for trenchless rehabilitation and pipe bursting technology services, replacement of City of Clearwater’s water main system in the annual not-to-exceed amount of $3,000,000.00 with the option for three one-year renewals at the City’s discretion in accordance with Clearwater Code of Ordinances Section 2.563(1)(c), Piggyback, and authorize the appropriate officials to execute same. (consent)
Body
SUMMARY:
This contract will apply trenchless rehabilitation and pipe bursting technology, providing full-service pipe bursting and slip lining of water mains. This technology minimizes amount of open trench excavation needed to replace pipelines. The pipe bursting portion of the project includes replacing 4, 6 and 8-inch cast iron water pipes, inclusive of water service lines, bypassing, valves, fittings, fire hydrants, and restoration work in the best interest for City Clearwater’s water distribution system. Contract shall be used in conjunction with City of Clearwater 18-0040-UT Task 12 CIP 17 and 19 water main project on Island Estates in addition to future trenchless pipe replacement projects.
Piggyback: City of Pompano Beach Broward County FL. Contract # E-15-22 - expires July 27, 2027, up to $3,000,000.00 annually for a total not-to-exceed amount of $12,000,000.00 for all years.
APPROPRIATION CODE AND AMOUNT:
3217321-546900-96721
Budgeted funds are available in CIP Project 96721 Water System R&R Maintenance.