SUBJECT/RECOMMENDATION:
Title
Approve Supplemental Work Order One (SWO 01) to Chen Moore and Associates, Inc., of St. Petersburg, FL, for North Beach Stormwater and Tidal Flooding Improvements project (24-0037-EN), in amount of $3,289,355.79, increasing contract from $1,291,598.00, to $4,580,953.79, pursuant to Request for Qualifications (RFQ) 50-24; and authorize the appropriate officials to execute same. (consent)
Body
SUMMARY:
North Clearwater Beach has experienced chronic flooding resulting from low roadway elevations, flat topography, aging drainage infrastructure, and tidal influences. These conditions affect neighborhood accessibility, public safety, and the ability of the existing stormwater system to recover following significant rainfall and coastal flooding events.
On July 10, 2025, City Council approved an initial work order with Chen Moore and Associates, Inc. (CMA), in the amount of $1,291,598.00, to advance engineering design, permitting, and bidding support for the North Beach Stormwater and Tidal Improvements project pursuant to RFQ 50-24. The original approach contemplated five new stormwater pump stations and one interconnection. The work order also included hydrologic and hydraulic (H&H) modeling, an alternatives analysis, and development of a coordinated grant funding and permitting strategy. During this council session, it was discussed that a future supplemental work order would be brought back to council for approval.
Post-storm damage assessments following Tropical Storm Debby and Hurricanes Helene and Milton provided additional information regarding properties impacted by historical flooding. The City incorporated this information into the ongoing H&H analysis and alternatives evaluation to identify improvements that would provide measurable flood reduction benefits to historically impacted properties while reducing reliance on individual pump stations.
The resulting Alternatives Analysis identified the preferred near-term flood mitigation approach. Rather than proceeding with the five original pump station configurations, the revised approach incorporates targeted stormwater conveyance improvements, drainage basin interconnections, larger outfalls, and two new pump stations to provide a more efficient and coordinated drainage system.
The initial work order funded significant efforts in securing grant funding to offset the costs of the project up to $23.95 million. As of today, the city has successfully secured $11.2 million in outside funding with another $12.75 million pending as Tier One under the FEMA Hazard Mitigation Grant Program (HMGP).
The North Beach improvements will be constructed through two complementary project components. The North Beach Flood Mitigation Project, for which the City is pursuing HMGP funding and is covered in the SWO 01, focuses on reducing flood risk and potential property damages associated with historical storm events. The Resilient Florida-funded improvements will build upon the flood mitigation project by incorporating additional measures to mitigate flooding and will be presented to Council later.
This work order builds upon the engineering completed under the previous authorization, incorporates feedback received from North Beach residents, and uses post-hurricane damage assessments to better target infrastructure investments.
Approval of SWO 01 will authorize CMA to advance the selected flood mitigation improvements through final design, permitting, grant coordination, and bidding assistance in preparation for future construction authorization. Construction phase engineering services are not included in this work order and will be presented for approval with the future construction contract.
CMA has confirmed that the initial work order and fees have an estimated unused $300,000 balance that will be used to offset the SWO 01 fees (SWO 01 fees $3,589,355.79 minus $300,000 unused balance from original WO=$3,289,355.79, amount of requested increase).
This project is estimated to be completed 556 working days from the issuance of notice-to-proceed.
The next steps are to bring a Council item forward to approve the Resilient Florida Grant award, the EPA Community Grant Award and another supplemental work order for the Resilient Florida project.
The total project budget for North Beach Pump Stations is anticipated to be $67,375,540. The following represents the total previously allocated and future funding identified in the published FY2026/27 Capital Improvement Program:
• Stormwater Fund Revenue: $56,175,540
• State Environmental Grant Funding: $11,200,000
The total project budget includes the City's planned multi-year stormwater improvements, including pump stations, stormwater conveyance upgrades, outfall improvements, and future resilience measures.
• Resilient Florida Grant: $6,450,000 awarded for North Beach Resilience Improvements. City staff are working toward execution of the grant agreement, which will be presented to City Council for approval in the near future.
• State Appropriation: $3,000,000 award and approved for North Beach improvements. No City match required.
• EPA Community Grant: $1,750,000 awarded. City staff are working toward execution of the grant agreement, which will be presented to City Council for approval in the near future. Staff successfully substantiated a request to waive the required 25% cost-share, resulting in a $437,500 reduction in the City's anticipated matching obligation. Staff are coordinating with EPA to determine whether the grant funding may be applied toward engineering design costs.
• FEMA Hazard Mitigation Grant Program (HMGP): $12,750,000 forecasted but not yet awarded, subject to FEMA approval and applicable grant requirements.
Grant Funding Status
Grant Outside-Share City-Share Total Status
Resilient FL Grant $6,450,000 $6,450,000 $12,900,00 Awarded
State Appropriation $3,000,000 $0 $3,000,000 Awarded
EPA Community $1,750,000 $0 $1,750,000 Awarded
HMGP $12,750,000 $4,250,000 $17,000,000 Pending
Total $23,950,000 $10,700,000 $34,650,000
APPROPRIATION CODE AND AMOUNT:
ENST240001-DSGN-PROSVC - $3,289,355.79
Funding for this work order is available in Capital Improvement Project ENST240001, North Beach Pump Stations.
USE OF RESERVE FUNDS:
N/A
STRATEGIC PRIORITY:



1.1 - High Performing Government: Utilizes data-driven analysis, including documented storm impacts and damage assessments, to guide infrastructure investments and maximize public benefit.
1.2 - High Performing Government: Protects and improves critical public infrastructure and mobility systems through strategic stormwater investments that strengthen long-term community resilience.
1.3 - High Performing Government: Leverages federal and state grant funding to maximize infrastructure investment, reduce local financial burden, and support responsible stewardship of public resources.
3.3 - Community Well-Being: Incorporates proactive public outreach throughout design and construction to keep residents informed, minimize disruptions, address community concerns, and build trust throughout project delivery.
4.1 - Environmental Stewardship: Advances science-based coastal resilience by reducing flood vulnerability and improving stormwater quality before discharge to sensitive receiving waters surrounding Caladesi Island State Park, protecting both the natural and built environment.