File #: ID#26-1341    Version: 1 Name: Approve Pier 60 (25-0007-PR) repair approach and Supplemental One work order to WSP for full deisgn.
Type: Action Item Status: Agenda Ready
File created: 10/27/2026 In control: Public Works
On agenda: 11/30/2026 Final action:
Title: Approve WSP USA, Inc.'s recommended rehabilitation approach for the Pier 60 Repair Project (25-0007-PR), and approve Supplemental One work order with WSP USA, Inc., to complete final design and permitting services in the amount of $154,825.00, increasing purchase order from $708,227.00 to $863,052.00 pursuant to RFQ 55-25, and authorize the appropriate officials to execute same. (consent)
Attachments: 1. Pier 60 Alternatives Report_9-21-26.pdf, 2. Clearwater_Pier 60_WSP Inspection Report_6-18-26.pdf, 3. Pier 60 Scope (WSP) 3-11-26 S&S.pdf, 4. Pier 60 Scope - Final Design 11-03-26 - WSP Signed.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT/RECOMMENDATION:

Title

Approve WSP USA, Inc.'s recommended rehabilitation approach for the Pier 60 Repair Project (25-0007-PR), and approve Supplemental One work order with WSP USA, Inc., to complete final design and permitting services in the amount of $154,825.00, increasing purchase order from $708,227.00 to $863,052.00 pursuant to RFQ 55-25, and authorize the appropriate officials to execute same. (consent)

Body

SUMMARY:

Pier 60, a well-known landmark on Clearwater Beach, sustained significant damage from Hurricanes Idalia, Helene, and Milton, particularly to the western T-section, structural connections, railings, and utilities.

At the June 2, 2025, Council Work Session, staff presented three repair alternatives for the T-section, including replacement in kind, removal of the T-section, and renovation incorporating frangible decking and new shade structures.

On March 30, 2026, City Council approved a $708,227 work order with WSP USA, Inc., pursuant to RFQ 55-25, for an in-depth structural investigation, alternatives analysis, and development of rehabilitation plans through 60% design.

WSP completed its investigation and submitted the Pier 60 Rehabilitation Alternatives Report on September 21, 2026. The investigation determined that the existing prestressed concrete deck panels, piles, and pile caps are generally in serviceable condition, with deterioration primarily concentrated at expansion joints, structural connections, and localized concrete areas.

The engineering services required for Pier 60 extend beyond conventional design and include extensive above and below water inspections, structural and coastal analyses, and evaluation of multiple repair, replacement, and resiliency alternatives. These investigations were necessary to assess the existing structure, identify storm-related deficiencies, evaluate long-term performance, and determine the most practical and cost-effective rehabilitation approach.

The comprehensive evaluation identified opportunities to preserve serviceable structural components rather than pursue extensive reconstruction, reducing anticipated construction costs while addressing long-term maintenance and storm resiliency. Accordingly, the original engineering authorization includes a substantial investment in investigation and alternatives analysis that would not typically be required for a conventional new construction project.

As part of the evaluation, WSP assessed the feasibility of incorporating frangible decking to improve storm resilience. However, the existing deck panels are transversely post-tensioned, and removing or modifying portions of the deck would alter the existing structural load paths and potentially increase loading on adjacent structural components. Retrofitting frangible decking would require extensive structural analysis and modifications, potentially extending construction duration, increasing costs, and presenting additional permitting challenges.

Based on these findings, WSP does not recommend frangible decking for the existing pier structure. Instead, WSP recommends rehabilitating the existing structure and improving its ability to accommodate storm-induced movement through enhanced structural connections and expansion joints.

WSP evaluated three rehabilitation alternatives:

•                     Minimum necessary repairs - $2,620,836: Targeted repairs to extend the existing structure's service life.

•                     WSP recommended repairs - $4,915,174: Comprehensive rehabilitation intended to extend the pier's service life by approximately 30 years.

•                     Maximum service life repairs - $12,160,318: Extensive structural replacement and resiliency improvements.

Staff recommend proceeding with WSP's recommended rehabilitation alternative, estimated at $5 million in construction costs. The proposed improvements include replacement of deteriorated concrete topping and closure pours, enhanced expansion joints, realignment of displaced T-section deck panels, replacement of bearing pads and railings, localized pile and pile cap repairs, replacement of the bait house catwalk, and electrical and utility improvements. An updated construction cost estimate will be developed during final design to establish a comprehensive project budget.

This approach preserves serviceable structural components while addressing storm-related deficiencies, improving long-term durability, and reducing construction costs compared to more extensive replacement alternatives.

The proposed supplemental work order will advance the selected rehabilitation plans from 60% through final signed and sealed construction documents, including structural, architectural, electrical, utility, accessibility, and permitting requirements. Design is estimated to be approximately four months.

Construction is estimated to require approximately 12 months. The project will be coordinated with the FEMA extension deadline of September 28, 2028, to minimize potential impacts to reimbursement eligibility and project funding. In addition to possible FEMA reimbursement the Parks and Recreation Department may be submitting a TDC grant application on January 15th, which could help cover half of any amount of this repair project that is not reimbursed by FEMA, as well as funds to make Pier 60 enhancements. The enhancements may include additional decorative lighting, turtle friendly lighting system, improvements to the bait house restrooms, decorative entry way and signage to pier entrance, improvements to pier shade structures and new pier furniture and amenities.

Total project funding of $5,000,000 is identified and available, funded by revenues from the General Fund.

APPROPRIATION CODE AND AMOUNT:

3157575-561300-M2505 $154,825.00

Funding for this work order is available in capital project M2505, Pier 60 R&R, funded by revenues from the General Fund.

STRATEGIC PRIORITY:

This item supports Strategic Plan Objectives:

•                     1.2: Maintain public infrastructure through systematic management efforts.

•                     2.3: Promote Clearwater as a premier destination for entertainment, cultural experiences, and tourism.

•                     3.2: Preserve community livability through responsible development standards and targeted revitalization.