Legislation Details

File #: ID#26-1411    Version: 1 Name: Approve a Guaranteed Maximum Price (GMP) proposal from PJ Hayes Inc. dba Tandem Construction, of Sarasota, FL, for the Eddie C. Moore Complex Renovations project (25-0032-PR).
Type: Action Item Status: Public Hearing
File created: 11/9/2026 In control: Public Works
On agenda: 11/17/2026 Final action:
Title: Approve a Guaranteed Maximum Price (GMP) proposal from PJ Hayes Inc. dba Tandem Construction, of Sarasota, FL, for the Eddie C. Moore Complex Renovations project (25-0032-PR), in the amount of $20,982,456.64, pursuant to RFQ 13-26, Construction Manager at Risk (CMAR) Services; transfer $12,940,000 from retained earnings at first quarter to Eddie C. Moore Complex Renovations project (C2510) and authorize the appropriate officials to execute same.
Attachments: 1. Eddie C Moore Complex Reno GMP 11.16.26.pdf, 2. CMAR Contract_Executed.pdf, 3. 13-26_CMAR Pressbox and Sports Field at Eddie C Moore.pdf, 4. Eddie_C_Moore_Presentation_Views.pdf, 5. Eddie_C_Moore_Presentation_Views
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT/RECOMMENDATION:

Title

Approve a Guaranteed Maximum Price (GMP) proposal from PJ Hayes Inc. dba Tandem Construction, of Sarasota, FL, for the Eddie C. Moore Complex Renovations project (25-0032-PR), in the amount of $20,982,456.64, pursuant to RFQ 13-26, Construction Manager at Risk (CMAR) Services; transfer $12,940,000 from retained earnings at first quarter to Eddie C. Moore Complex Renovations project (C2510) and authorize the appropriate officials to execute same.

Body

SUMMARY:

The Eddie C. Moore Complex includes fields 1-4 and the multipurpose fields east and west. The project includes construction of a new press box building to replace the existing one-story building and renovations to the surrounding athletic facilities to improve functionality, safety, accessibility, and overall operations. These improvements will enhance the complex’s ability to accommodate local recreational programs and regional and national sporting events, supporting Clearwater’s sports tourism industry.

On January 15, 2026, City Council approved a professional services agreement and work order with PBK Architects in the amount of $1,430,149.00 for design services pursuant to Request for Qualifications (RFQ) 41-25 and the transfer of $740,000 from Athletic Fields R & R (M2207) to E.C. Moore Renovations (C2510) at mid-year.

On March 30, 2026, City Council approved a Construction Manager at Risk (CMAR) agreement and preconstruction services proposal with PJ Hayes Inc. dba Tandem Construction in the amount of $93,882.00 pursuant to RFQ 13-26. Preconstruction services included cost estimating, constructability reviews, value engineering, subcontractor procurement, scheduling, and development of a Guaranteed Maximum Price (GMP).

The GMP provides for construction of a new two-story, approximately 7,023-square-foot press box building with observation deck, expanded restroom facilities, multipurpose spaces, an elevator, and associated amenities. Additional improvements include eight new dugouts, spectator seating and bleachers, batting cages, scoreboards, sports lighting, fencing, landscaping, irrigation, stormwater management, and utility improvements. The multipurpose fields will also receive grading, drainage, fencing, natural turf playing fields and LED lighting improvements.

During the preconstruction phase, Tandem Construction worked with PBK Architects and City staff to evaluate construction costs, identify potential cost savings, and coordinate project requirements. The GMP was developed based on 100% construction documents and includes construction labor, materials, equipment, general requirements, construction contingencies, insurance, bonding, and construction management fees.

On November 5, Tandem Construction submitted an initial GMP of $23,596,634.05.  Subsequently staff met with Tandem Construction on November 9, to discuss value engineer (VE) options and negotiate the GMP to a not to exceed value of $21 million. Tandem provided on November 16 an updated GMP of $20,982,456.64. The (VE) process identified several cost-saving alternatives while maintaining the project’s functionality and performance. These alternatives include substituting more economical canopy systems, dugout benches and helmet/bat racks; utilizing broom-finished concrete in lieu of epoxy flooring at the dugouts; reducing the root-zone depth of turf at the multipurpose fields; modifying some HVAC control systems; and possibly removing the upgrade to lighting systems for fields 5 through 7.

Construction is anticipated to commence in March 2027, with substantial completion scheduled for February 2028, ahead of the tournament season.

This project includes a new press box, expanded restrooms and enhancements to the complex as mentioned above. Future operating costs for these improvements will remain relatively stable, since there will be no increase in personnel costs and electrical savings from the installation of energy-efficient lighting systems. Total estimated increase in operating costs of $2,000 per month should be offset by new revenue generated from additional tournaments and rentals held at the Complex.

The project was previously budgeted at $21,850,000 with $740,000 in additional funds approved at first quarter, for a new budget of $22,590,000, of which $7,750,000.00 is funded from a Tourist Development Council (TDC) grant and the remainder from General Fund revenues. Funding for the project was budgeted for and was programmed across fiscal years 2026/27 through 2028/29.

To balance the overall city budget for FY 2026/2027, programmed general funds for this project of $12,940,000 were removed. Staff are requesting that council approve reappropriating general fund reserves in the amount of $12,940,000 for this project and that the budget be amended in the first quarter to reflect this change.

If approved this item will need to be advertised and brought back to the council for final allocation of funds at the next city council meeting.

APPROPRIATION CODE AND AMOUNT:

A first quarter budget amendment will allocate $12,940,000 from General Fund reserves, transferring it to capital project C2510, E.C. Moore Renovations, to provide additional funding needed for this construction contract.

USE OF RESERVE FUNDS:

Funding for this contract will be provided by a first quarter budget amendment allocating General Fund reserves in the amount of $12,940,000 to capital improvement project C2510, E.C. Moore Renovations. Inclusive of this item if approved, a net total of $12,940,000 of General Fund reserves has been used to date to fund expenditures in the 2026/27 operating budget. The remaining balance in General Fund reserves after the 8.5% reserve is approximately $41.8 million, or 18.2% of the current General Fund operating budget.

STRATEGIC PRIORITY:

High Performing Government -

1.2 Maintain public infrastructure, mobility systems, natural lands, environmental resources, and historic features through systematic management efforts.

 

Economic & Housing Opportunity -

2.3 Promote Clearwater as a premier destination for entertainment, cultural experiences, tourism, and national sporting events.