File #: ID#26-0472    Version: 1 Name: Award a construction contract to Concrete Protection & Restoration, LLC, in the amount of $186,318 for the Garden Avenue Garage Restoration project (25-0013-EN) and authorize the appropriate officials to execute same
Type: Action Item Status: Agenda Ready
File created: 4/7/2026 In control: Public Works
On agenda: 5/4/2026 Final action:
Title: Award a construction contract to Concrete Protection and Restoration, LLC, for the Garden Avenue Garage Restoration project (25-0013-EN), in the amount of $186,318.00 pursuant to Invitation to Bid 25-0013-EN and authorize the appropriate officials to execute same. (consent)
Indexes: 1. High Performing Government , 2. Economic & Housing Opportunity
Attachments: 1. Notice of Intent to Award Garden Avenue Parking Garage, 2. Vendor Bid Tab Pricing, Garden Avenue Parking Garage, 3. Concrete Protection & Restoration Section V, 4. Garden Avenue Garage Restoration project map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT/RECOMMENDATION:

Title

Award a construction contract to Concrete Protection and Restoration, LLC, for the Garden Avenue Garage Restoration project (25-0013-EN), in the amount of $186,318.00 pursuant to Invitation to Bid 25-0013-EN and authorize the appropriate officials to execute same. (consent)

Body

SUMMARY: 

A condition assessment of the Garden Avenue parking garage, which provides 250 parking spaces in downtown Clearwater, identified necessary preventative maintenance repairs totaling $186,318.00 to preserve the structure’s useful life and avoid more costly issues in the future. This project consists of:

a.                     Concrete floor repairs

b.                     Concrete ceiling repairs

c.                     Concrete beam and joist repairs

d.                     Concrete column repairs

e.                     Replacement of precast joint sealant

f.                     General waterproofing repairs

g.                     Cold galvanizing steel connections

h.                     Restripe roof level to match existing layout

 

On February 4, 2026, Invitation to Bid (ITB) 25-0013-EN was issued and the city receive eight  responsive and responsible bids on March 11, 2026.  Concrete Protection & Restoration LLC submitted the lowest responsive and responsible bid in accordance with the plans and specifications. 

 

Construction will be completed in phases to allow as much parking as possible to remain available during the restoration work.  The total project duration is 120 days.

The Parking Systems Division operates and maintains the Garden Avenue parking garage

 

APPROPRIATION CODE AND AMOUNT:

Funding for this construction contract is available in capital improvement project ENPK180003, Parking Facilities, funded by revenues from the Parking Enterprise Fund.

 

STRATEGIC PRIORITY:

1.2 - Maintain public infrastructure, mobility systems, natural lands, environmental resources, and historical features through systematic management efforts.1.3 - Adopt responsive levels of service for public facilities and amenities, and identify resources required to sustain that level of service. 2.3 - Promote Clearwater as a premier destination for entertainment, cultural experiences, tourism, and national sporting events.