Award a construction contract to KAT Construction and Materials Inc. of Brooksville, Florida, for Invitation to Bid (ITB) 23-0013-UT Northeast WRF Digester Repairs, in the amount of $7,083,870.00; approve Supplemental Work Order One with Black and Veatch in the amount of $495,887.00 pursuant to RFQ 34-23, Engineer of Record Consulting Service, Continuing Contract; and authorize the appropriate officials to execute same. (consent)
Body
SUMMARY:
The City utilizes an anaerobic digester at its Northeast Water Reclamation Facility (NEWRF) that converts organic matter into stabilized biosolids and methane (biogas). In 2023, the cover for the digester that floats on the biogas became titled and damaged the cover and the structure of the digester.
On January 18, 2024, City Council approved an initial work order to Engineer of Record Black & Veatch Corporation for design and bidding services for the NEWRF Digester Repairs in the amount of $178,000.00.
The project scope includes addressing the out-of-service primary digester at the Northeast Water Reclamation Facility (NEWRF), located at 3290 State Road 580, Clearwater, FL 33761. The work involves repairs to the primary anaerobic digester, including draining and cleaning of the digester, repair and reinstallation of the digester cover, interior and exterior coatings, concrete repairs, and replacement of plug valves, piping, mixing nozzles and associated appurtenances. The work also includes a bid alternate for a new digester cover if determined necessary. This project supports the continued reliable treatment and stabilization of biosolids at the NEWRF.
The Engineering Department issued ITB 23-0013-UT, which closed on September 9, 2026. The lowest responsive, responsible bid, submitted in accordance with the plans and specifications, was from KAT Construction & Materials Inc. in the amount of $4,084,700.00 for the base bid, plus a 10% Owner’s Contingency Allowance of $408,470.00 and $2,590,700.00 for the Bid Alternate (New Digester Cover), for a total contract amount of $7,083,870.00. EOR Black & Veatch Corporation evaluated the bids and recommends awarding the contract, including the bid alternate, to KAT Construction & Materials Inc.
Supplemental Work Order One is for engineering and inspection services during construction in the amount of $495,887.00, for a new total work order value of $673,887.00. The construction duration is 365 consecutive calendar days from the issuance of the Notice to Proceed. The City of Clearwater’s Public Utilities Department is responsible for owning, operating, and maintaining the Northeast Water Reclamation Facility.
The City is currently working towards consolidating the current three water reclamation facilities into a single water reclamation facility at NEWRF. The City is consolidating these facilities to improve long-term reliability and resilience, reduce vulnerability to coastal hazards, and position the system for efficient investment over the planning horizon. The master plan notes that the Northeast Water Reclamation Facility is least likely to be impacted by climate variability, while sea-level rise and storm surge can significantly inundate the other coastal facilities. It also highlights that the NEWRF site has room to expand and can reduce biosolids hauling because it already treats thickened sludge from the East Water Reclamation Facility (WRF). City Council approved the full consolidation of the Marshall Street WRF and the East WRF to the NEWRF March 3, 2023, which then set the direction for planning and design around a single, primary treatment facility.
Once this project is complete, the newly refurbished digester will have an expected life expectancy of 25-years, and be an integral part of the consolidated WRF
APPROPRIATION CODE AND AMOUNT:
3277327-561300-M1906
Funds are available in capital improvement project 327-M1906, Northeast Plant R&R, to fund this contract. First quarter budget amendments will transfer $429,856.43 from project 3217321-M2103, Utilities Building & Maintenance to 3277327-M1906, Northeast Plant R&R, and $4,493,170.00 from project 3217321-M2603, Water, RCW and Well Repair and Improvements to 3277327-M1906, Northeast Plant R&R to provide additional project funding.
A future budget amendment in the amount of $2,590,700.00 may be needed if the bid alternate is exercised. These projects are funded by revenues from the Water and Sewer Utility Enterprise Fund.
STRATEGIC PRIORITY:
This project aligns with the Council’s Strategic Plan objective of achieving a High Performing Government through proactive maintenance of public infrastructure. Approval of this construction award and EOR Supplemental 1 work order will help ensure the continued efficiency and reliability of the City’s wastewater treatment operations.