File #: ID#14-568    Version: 1 Name: Solid Waste Transfer Station Rebuild
Type: Action Item Status: Passed
File created: 9/29/2014 In control: Solid Waste
On agenda: 10/13/2014 Final action: 10/15/2014
Title: Approve establishing a new Capital Improvement Project entitled Transfer Station Rebuild (CIP 315-96447) for $1,000,000, to be funded from unappropriated retained earnings of the Solid Waste Fund, for preliminary site work to include but not limited to geotechnical surveys, land surveys, and preliminary design needed for the new Transfer Station facility. (consent)
SUBJECT/RECOMMENDATION:
Title
Approve establishing a new Capital Improvement Project entitled Transfer Station Rebuild (CIP 315-96447) for $1,000,000, to be funded from unappropriated retained earnings of the Solid Waste Fund, for preliminary site work to include but not limited to geotechnical surveys, land surveys, and preliminary design needed for the new Transfer Station facility. (consent)
 
Body
SUMMARY:  
Since 1970, the City of Clearwater has operated a centrally-located solid waste transfer station.  This facility is used by department route trucks to increase efficiency, by allowing the trucks to dump quickly and return to route collection.
At the time of its construction, the Transfer Station facility was projected to last for twenty years and handle up to 400 tons of waste weekly.  Currently the facility is forty-four years old and is depended upon to handle an average of 340 tons of waste daily.  The facility's age, increased tonnage, increased maintenance requirements, and deterioration of the building and its foundation necessitates that a new facility be constructed.
After preliminary designs and surveys are completed, the department will present to Council a total cost for the project. The total cost of the project is expected to be in the range of $18 million to $20 million.
 
APPROPRIATION CODE AND AMOUNT:
0-424-00000-389902 Unappropriated Retained Earnings
 
 
USE OF RESERVE FUNDS:  