Legislation Details

File #: ID#26-1307    Version: 1 Name: Authorize an increase in the contract amount with Thornton Tomasetti,
Type: Action Item Status: Agenda Ready
File created: 10/20/2026 In control: City Attorney
On agenda: 11/30/2026 Final action:
Title: Authorize an increase in the contract amount with Thornton Tomasetti, Inc., for expert witness and engineering consulting services in connection with the City's pending construction defect litigation against Stantec, Inc, from $20,000 to a total not to exceed $140,000, and authorize the appropriate officials to execute same. (consent)
Attachments: 1. ThorntonTomasettiAgreement2026
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT/RECOMMENDATION:

Title

Authorize an increase in the contract amount with Thornton Tomasetti, Inc., for expert witness and engineering consulting services in connection with the City's pending construction defect litigation against Stantec, Inc, from $20,000 to a total not to exceed $140,000, and authorize the appropriate officials to execute same. (consent)

 

Body

SUMMARY: 

The City hired Stantec, Inc., to design Coachman Park.  The City hired Skanska USA to construct Coachman Park as a construction manager at risk (CMAR).  After the project was completed, the City identified certain design and construction defects.  On February 20, 2025, City Council authorized the filing of a lawsuit against Stantec to recover damages associated with these defects.  The City retained Gray Robinson to provide legal representation in this lawsuit.

 

The City Attorney's Office retained Thornton Tomasetti, Inc., an engineering consulting firm, to provide expert witness and engineering consulting services in connection with the litigation.  The City Attorney previously authorized an initial expenditure of up to $20,000 for these services.

 

The parties participated in mediation but were unable to reach a resolution.  As a result, the litigation is proceeding, with upcoming discovery deadlines requiring additional expert analysis and the preparation of an expert report to support the City's claims at trial, which is currently scheduled for August of 2027.

 

At the request of outside counsel, the City Attorney's Office is requesting authorization to increase the total contract amount with Thornton Tomasetti, Inc., by $120,000, for a total amount not to exceed $140,000.  The additional funding will allow the expert to complete the necessary engineering analysis, prepare the expert report, and provide continued litigation support as the case proceeds toward trial.

 

The City Attorney recommends approval of the increased expenditure to ensure the City is adequately prepared to pursue its claims. The actual cost may be less depending on the progression of the litigation.  No expenditures exceeding the authorized amount will be incurred without further Council approval.

 

The item is exempt from bidding pursuant to Section 2.563(1)(g), Clearwater Code of Ordinances.

 

APPROPRIATION CODE AND AMOUNT:

Funds are available in Central Insurance Fund cost code 5907590-545900, Insurance Claims-Liability, for this contract.