SUBJECT/RECOMMENDATION:
Title
Approve a work order to Engineer of Record (EOR) Tetra Tech, Inc. in the amount of $99,980 for the Reclaimed Booster Pump Station Chlorine Control Improvements Project (16-0001-UT) and authorize the appropriate officials to execute same. (consent)
Body
SUMMARY:
This work order provides for the evaluation of alternatives, design, permitting, and bidding of improvements at the Skycrest, Union and Drew Street Reclaimed Water Pump Stations.
The design phase is anticipated to be completed by December 2016, followed up by the construction phase currently anticipated to begin in April 2017.
Tetra Tech, Inc. is one of the City’s Engineers-of-record, and this work order was negotiated in accordance with the Consultants Competitive Negotiations Act.
APPROPRIATION CODE AND AMOUNT:
0327-96654-561300-535-000-0000 $99,980
Funding is available in Utility Renewal and Replacement Program project 0327-96654, Facilities Upgrade and Improvements to fund this project.